Case Study

37-39 East Cheap

A Central London Office Refurbishment.

PROJECT WORK


Levels 01 – 05.
Corporate office +

new ground floor reception to service office,

ground and lower ground levels

plus a new lift to serve the offices.

LOCATION

CENTRAL LONDON

PROJECT VALUE


£500K

£500k

Project Value

24 Weeks

Project Duration

Project Details

The works consists of the following:

  • LV distribution throughout the building.

  • Containment throughout the building for LV sub-mains, LV final circuits, IT cabling, security cabling, BMS cabling, fire detection and voice evacuation cabling and controls, including trunking, conduits, high-level tray and trunking.

  • Cat 6, structured cabling throughout the building.

  • Small power installation including underfloor trunking, and floor boxes.

  • Electrical connections to mechanical plant.

  • General/emergency and feature lighting

  • Design and installation of new fire alarm system, detection, and interfaces with other systems.

  • Access control.

  • Intercom.

  • Earthing system.

  • Fire stopping

Our Accreditations

We have worked hard to achieve the following accreditations for the Company and the relevant person within our Team, which Demonstrate our desire to be fully conversant & compliant to deliver your project.

Member Safe Contractor

VME Are proudly supported by HCS Safety Advisors:

VME Mechanical & Electrical Services Ltd, Unit 4 Old Farm Court, Nursling Street, Rownhams, Southampton, Hampshire, SO16 0AJ

VME Mechanical & Electrical Services Ltd, Unit 4 Old Farm Court, Nursling Street, Rownhams, Southampton,

Hampshire, SO16 0AJ

Copyright 2023 PFMR Ltd : All Rights Reserved